Opinion · Washington Supreme Court
Considine v. Gallagher
31 Wash. 669
- Type
- Opinion
- Court
- Washington Supreme Court
- Jurisdiction
- Washington
- Date
- 1903-04-29
- Topic
- general
The opinion of the court was delivered by Fullerton, C. J. —The respondent, Considine, entered into a contract with the defendant, Gallagher, by the terms of which the defendant undertook to furnish all of the necessary materials and construct for the respondent a dwelling house according to certain plans and specifications agreed upon between the parties for a fixed consideration. To secure the faithful performance of the work, the defendant entered into a bond, with the appellant as surety, in the sum of two thousand dollars, conditioned that he would carry out the contract. The defendant thereafter entered upon the prosecution of the work and partially completed the same, finally abandoning it before completion. The respondent thereupon, after notifying the surety to complete it, and after its refusal to do so, completed the building himself at a cost exceeding the original contract price by more than the amount of the bond.
Citator
UpLaw has not yet analyzed Considine v. Gallagher. The absence of a flag is not a finding that it is good law.
- Cited by
- 6 opinions
The opinion of the court was delivered by
Fullerton, C. J.—The respondent, Considine, entered into a contract with the defendant, Gallagher, by the terms of which the defendant undertook to furnish all of the necessary materials and construct for the respondent a dwelling house according to certain plans and specifications agreed upon between the parties for a fixed consideration. To secure the faithful performance of the work, the defendant entered into a bond, with the appellant as surety, in the sum of two thousand dollars, conditioned that he would carry out the contract. The defendant thereafter entered upon the prosecution of the work and partially completed the same, finally abandoning it before completion. The respondent thereupon, after notifying the surety to complete it, and after its refusal to do so, completed the building himself at a cost exceeding the original contract price by more than the amount of the bond. He brought this action upon the bond to recover for the loss to the amount of the penalty named in the bond.
A demurrer was interposed to the complaint on the ground that it did not state facts sufficient to constitute a cause of action, and overruled by the trial court, which ruling constitutes the first error assigned. The complaint averred that the building contract was entered into on the 12th day of December, 1900, while the bond as set out
The other errors assigned are based upon the sufficiency of the evidence to support the findings of fact, but, as no exceptions to the findings were taken, they cannot be considered.
The judgment appealed from is affirmed.
Dunbab, Hadley, Andebs and Mount, JJ., concur.