Opinion · Court of Appeals for the Tenth Circuit
United States Fidelity & Guaranty Co. v. American State Bank
372 F.2d 449
- Type
- Opinion
- Court
- Court of Appeals for the Tenth Circuit
- Jurisdiction
- Federal
- Date
- 1967-02-10
- Topic
- general
DAVID T. LEWIS, Circuit Judge. This case reaches us as a Rule 54(b) offshoot, Fed.R.Civ.P., in an original ac*450tion brought under the Miller Act, 40 U.S.C. §§ 270a and 270b, by the United States for the use and benefit of Flint Steel Corporation, a subcontractor, against the PLS Company, a joint venture engaged as prime contractor on a federal project at Ft. Sill, Oklahoma. The United States Fidelity & Guaranty Company was joined as party defendant as surety on the Miller Act bonds required of PLS for both payment and performance.
Citator
UpLaw has not yet analyzed United States Fidelity & Guaranty Co. v. American State Bank. The absence of a flag is not a finding that it is good law.
- Cited by
- 9 opinions
UNITED STATES FIDELITY GUAR. v. AM. ST. BK.,372 F.2d 449(10th Cir. 1967)
UNITED STATES FIDELITY GUARANTY COMPANY, Appellant, v. The AMERICAN
STATE BANK, Frank Farris, Howe Sound Company, Murray Director Affiliates,
Inc., and Security National Bank of Kansas City, Kansas, Appellees.
No. 8515.
United States Court of Appeals, Tenth Circuit.
February 10, 1967.
Coleman H. Hayes and John H. Cantrell, Oklahoma City, Okla. (Wm. J. Holloway, Jr., Crowe, Boxley, Dunlevy, Thweatt, Swinford Johnson, Monnet, Hayes, Bullis, Grubb Thompson, and Cantrell, Douglass, Thompson Wilson, Oklahoma City, Okla., on the brief with them), for appellees.
Before PICKETT, LEWIS and HICKEY, Circuit Judges.
Although the full scope of this appeal has required the parties to present arguments touching upon the jurisdictional and venue aspects of the Miller Act, the requirements of Rules 4(f) and 14, Fed.R.Civ.P., as they apply to the Miller Act, and the availability of the Oklahoma long-arm statute in such cases, we deem a threshold question to be dispositive. Did the court err in dismissing the third-party complaint when it became apparent that the appellant surety's claim against appellees was founded on the performance bond and was totally unrelated to the payment bond on which the use plaintiff brought the original action? We hold that the court did not err and affirm the judgment.
In Limerick v. T.F. Scholes, Inc.,292 F.2d 195, this court held it proper under the Miller Act to allow a third-party complaint by the surety wherein it was alleged that the third-party defendants had agreed to indemnify the prime contractor for any failure of the sub-contractor to perform and that the claim in the main action was predicated on the non-performance of the sub-contractor. InLimerickthe amount claimed by the use plaintiff was the identical amount for which the indemnifying third parties would be liable and the fact of liability of the third parties was dependent upon the success of the use plaintiff in the main action. In the case at bar, in contrast, no attempt is made to pass on to third parties all or part of the claim asserted against the original defendants. The original suit is on a payment bond. The third-party complaint is for indemnification for losses on a performance bond.1Under the Miller Act these bonds represent separate obligations running to separate obligees; to persons supplying materials and labor in the case of the payment bond and to the government of the United States in the case of the performance bond. Here, regardless of the success or failure of the use plaintiff's cause, the appellant surety's claims against appellees would persist as an entirely independent claim. The fact that the third-party claim arises against the same general background as the main claim is not enough to allow application of Rule 14 to independent claims. Horn v. Daniel, 10 Cir.,315 F.2d 471; 3 Moore, Federal Practice ¶ 14.07.
Affirmed.Page 451Page 470
- In the third-party complaint, surety asked for $400,000 as its cost of taking over and completing the project for PLS Company, $400,000 for punitive damages, and $40,000 for attorney's fees. The prayer for damages did not mention surety's potential amount of liability on the payment bond. ↩