PER CURIAM. This diversity action, tried without a jury in the United States District Court for the Eastern District of Missouri, resulted in a judgment in favor of plaintiffs in the amount of $43,000 and interest. Defendant has appealed, making no assertion that a mistake of law has been' committed, but rather contending, in ef-*716feet, that the trial court’s findings of fact are clearly erroneous. By a written contract, plaintiffs had agreed to construct a sewage treatment plant, sewers and appurtenances in and upon the land of defendant at or near Owego, New York. Plaintiffs’ trial theory was that during the course of construction of the project they were required to perform certain additional and extra work not a part of the original contract, for which defendant had promised and agreed to pay.

Citator

UpLaw has not yet analyzed Warnecke v. MacDonald Construction Co.. The absence of a flag is not a finding that it is good law.

Cited by
4 opinions